Title: A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE A CONTRACT FOR PROFESSIONAL CONSULTING SERVICES BETWEEN THE CITY OF POMPANO BEACH AND CALVIN, GIORDANO & ASSOCIATES, INC. FOR SINGLE PROJECT CONTRACT FOR CONSTRUCTION, ENGINEERING & INSPECTION SERVICES FOR SW 36TH AVENUE SIDEWALK PROJECT; PROVIDING AN EFFECTIVE DATE. (Fiscal Impact: $109,970.61)
Indexes: 4.2.6. Install six foot wide sidewalk along the west side of SW 36th Avenue
Attachments: 1. Exhibit A-City Attorney's Communication 2016-1132, 2. Exhibit B-Resolution 2016-294, 3. Exhibit C:Consultant Agreement Calvin Giordano & Associates, Inc, 4. Exhibit D: Work Authorization 1-Scope of Work-Calvin Giordano & Associates,Inc., 5. Exhibit F:COI Calvin Giordano, 6. Exhibit E: 5-24-16 Commission Meeting-Agenda Item 3

title

A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE A CONTRACT FOR PROFESSIONAL CONSULTING SERVICES BETWEEN THE CITY OF POMPANO BEACH AND CALVIN, GIORDANO & ASSOCIATES, INC. FOR SINGLE PROJECT CONTRACT FOR CONSTRUCTION, ENGINEERING & INSPECTION SERVICES FOR SW 36TH AVENUE SIDEWALK PROJECT; PROVIDING AN EFFECTIVE DATE. 

(Fiscal Impact: $109,970.61)

 

staffcontact

(Staff Contact: Horacio Danovich/ Anthony Alhashemi)

 

summary

Summary Explanation/Background:

RFP E-18-16 was issued to select a single firm to provide Construction Engineering and Inspection (CEI) services to the City for the SW 36th Ave Sidewalk. The CEI services are required for contract inspection, administration, and materials sampling and testing for sidewalk and drainage construction, utility work, signage, and striping for the sidewalk project. This project will run along SW 36th Ave from 640’ North of West McNab Road to West Palm Aire Drive.

 

City Commission has approved the ranking order presented by the Selection/Evaluation on May 24th, 2016 (Agenda Item: 3) and the City has negotiated an agreed price with the highest-ranked firm, Calvin Giordano & Associates, Inc.

 

In order to begin construction, FDOT has made it a requirement to procure CEI (Construction Engineering & Inspection) services for the SW 36th Ave Sidewalks Improvement Project. FDOT will be providing partial funding for CEI services for the amount of $50,980.00.

 

Attachments:

Exhibit A: City Attorney's Communication 2016-1132

Exhibit B: Resolution 2016-294

Exhibit C: Consultant Agreement Calvin Giordano & Associates, Inc

Exhibit D: Work Authorization 1-Scope of Work-Calvin Giordano & Associates,Inc.

Exhibit E: 5-24-16 Commission Meeting-Agenda Item 3-Consent of Ranking Order for CEI

Services.

Exhibit F: Insurance

 

 

 

Origin of request for this action: Engineering Department

Fiscal impact and source of funding: $109,970.61 , Capital Improvements Funds,Account: 302-7503-589.65-03, CIP 14-225