File #: LN-430    Version: 1 Name:
Type: PZB Submission Status: Passed
File created: 3/29/2023 In control: Planning and Zoning Board
On agenda: 4/26/2023 Final action: 4/26/2023
Title: NE 19TH AVE MULTI-FAMILY PROJECT
Attachments: 1. PZB Documents 4-26-2023.zip, 2. PZB Drawings 4-26-2023.zip

boardname

PLANNING AND ZONING BOARD

Meeting Date: APRIL 26, 2023

 

title

NE 19TH AVE MULTI-FAMILY PROJECT

 

projectinfo

Request:                     Major Site Plan

P&Z#                     22-12000050

Owner:                     Progressive Pointe Boutique LLC

Project Location:                     NE 19th Ave

Folio Number:                     484236011570

Land Use Designation:                     ETOC (East Transit Overlay Corridor)

Zoning District:                     TO-EOD (Transit Oriented East Overlay District)

Commission District:                     3 (Alison Fournier)

Agent:                      Mike Amodio (954-788-3400 / mamodio@keithteam@gmail.com)

Project Planner:                     Saul Umana (954-786-4662 / saul.umana@copbfl.com)

 

otherinfo

 

 

Summary:                     

The applicant is requesting Major Site Plan approval in order to construct a new 37 unit multi-family development with a four-story building, with associated parking and landscaping. The project previously obtained approval from the Planning and Zoning Board in October of 2018. The development order expired prior to issuance of a Zoning Compliance Permit, and as a result the project must obtain new approval. The site is currently vacant. The total building footprint will be 11,000 square feet (sq. ft.) on a 27,500 sq. ft. (0.63 acre) site with 40% lot coverage.  Minor changes include additional landscaping and changes to the site grading, and ground floor height clearance. The Development Review Committee reviewed the subject site plan on January 18, 2023. In addition, the subject site plan received Major Design approval on April 4, 2023 by the Architectural Appearance Committee. 

The property is located on the east side of the NE 19th Ave between East Atlantic Blvd and NE 2nd Street.

 

 

 

 

SITE PLAN REVIEW STANDARDS

 

An application for a Major Site Plan or Minor Site Plan shall be approved only on a finding that there is competent substantial evidence in the record that the development, as proposed:

 

1. Is consistent with the land use designation in the comprehensive plan;

 

The property has a land use designation of  ETOC( East Transit Overlay Corridor). The proposed multiple-family residence use is a compatible use for this land use category. The Development is consistent with the City of Pompano Beach Comprehensive Plan, and the Future Land Use Element Goals, Objectives and Policies contained therein:

 

 Goal 01: The attainment of a living environment which provides the maximum physical, economic and social well-being for the City and its residents through the thoughtful and planned use and control of the natural and man-made environments that discourages urban sprawl, is energy efficient and reduces greenhouse gas emissions.

 

Goal 03: To provide structurally safe, affordable, uncrowded and otherwise adequate residential shelter for all existing and anticipated future residents of the City of Pompano Beach that utilize energy efficient, sustainable design, resilient construction techniques, materials and renewable energy resources.

 

Objective 01.04.00 - Major Corridor Land Use: Support and promote the intermix of residential and commercial uses along major traffic corridors.

 

Objective 01.14.00 - Smart Growth Initiative: The City will promote “Smart Growth” type initiatives providing for energy efficient development and land use patterns which also account for existing and future electrical power generation and transmission systems in an effort to discourage urban sprawl and reduce greenhouse gasses.

 

Policy 01.07.19 The City's land development code shall include provisions to encourage or enable a variety of housing opportunities in varying price ranges, including housing for low- and moderate-income families in large scale residential developments.

 

Policy 01.14.01 The City shall emphasize re-development and infill, which concentrates the growth and intensifies the land uses consistent with the availability of existing urban services and infrastructure in order to conserve natural and man-made resources.

 

2. Complies with the applicable district, use, and intensity and dimensional standards of this Code (Articles 3, 4, and 5);

 

Article 3: Zoning Districts

 

The proposed development complies with the intensity and dimensional standards for the Transit Oriented (Section 155.3701) and East Overlay District (Section 155.3709) zoning districts.

 

Article 4: Use Standards

 

The proposed development complies with the standards for a Multifamily Dwelling (Section 155.4202.C)

 

Article 5: Development Standards

 

See section 3 below.

 

3. Complies with the applicable development standards of this Code (Article 5);

 

The DRC and project applicant have worked together to present a project that satisfies the requirements of Article 5 for new development requiring Major Site Plan approval, with the exception of the conditions listed for approval.

 

As part of the Major Site Plan and Building Design application, the applicant has provided a narrative addressing how the project will achieve the required sustainability points. The project has met the required 10 sustainability points for residential development.

 

4. Complies with all other applicable standards in this Code;

 

The proposed site plan is in compliance with all other applicable standards of this Code.

 

5. Complies with all requirements or conditions of any prior applicable development orders or prior applicable approved plans on record.

 

The anticipated Development Order issued for project will supersede all other development orders previously issued for this project.

 

6.  The concurrency review has been completed in accordance with Chapter 154 (Planning) of the Code of Ordinances;

Based on the calculations below, the proposed project complies with concurrency requirements.

 

Based on the calculations below, the proposed project complies with concurrency requirements.

 

Wastewater Treatment Demand                    9,250         gallons per day *

Water Treatment Demand                             10,970.50  gallons per day *

Raw Water Demand                                      11,848.14  gallons per day *

Park Acreage Required                                 0.25

School Impacts                                             Staff has notified the applicant to obtain a Broward

                                                                     County School Capacity Availability Determination

                                                                     (SCAD) letter.

Transportation                                             Transit fees paid to the Broward County to meet                  

                                                                     Concurrency

Solid Waste Generation                              329.30lbs. per day (City has a contract with the Waste  

                                                                    Management for disposal of all solid waste through 

                                                                    2033)

 

 

* The City has adequate capacity to serve the proposed project.

 

7. Is designed to provide safe, adequate, paved vehicular access between buildings within the development and streets as identified on the Broward County Trafficways Plan;

 

The development is located on NE 19th Avenue, a street that is not identified on the Broward County Trafficways Plan. However, the project is designed to provide safe, adequate, and paved vehicular access to NE 19th Avenue with wide sidewalks and street trees to complete the pedestrian experience.

 

 8. Complies with any applicable hazardous material licensing requirements in the Broward County Wellfield Protection Ordinance;

 

The property is not located within a wellfield protection area as identified on the Broward County Wellfield Protection Zones map.

 

9. Complies with crime prevention security strengthening and CPTED standards for natural surveillance, natural access control, territorial reinforcement, maintenance and activity support;

 

As part of the Major Site plan and Building Design application, the applicant has developed a separate CPTED security plan, which addresses the CPTED standards for natural surveillance, natural access control, territorial reinforcement, maintenance and activity support.

 

10. Complies with adopted Fire Codes and Standards per City Code Section 95.02

 

The proposed site plan was reviewed by a Fire Plans Examiner during DRC and will be required to meet all applicable standards before building permits are approved.

 

11. Considers and mitigates any potential adverse impacts on environmentally sensitive lands identified by the City Comprehensive Plan or Broward County Land Use Plan.

 

The proposed development is not within an area that will have impact on environmentally sensitive lands as defined in the Broward County Land Use Plan.

 

12. Complies with the approved Transportation Corridor Study, unless in direct conflict with another Zoning code provision.

 

The proposed development is not located in any of the subject areas of the approved Transportation Corridor Study.

 

DEPARTMENT RECOMMENDATION

 

Pursuant to §155.2304.C, Applications Subject to Staff Recommendation, the Development Services Director has compiled the department reports from the Development Review Committee (DRC) meeting which are recorded on file with the Department of Development Services. Should the Board find that the application has provided competent, substantial evidence to satisfy the review standards for Major Site Plan approval, the Development Services Department recommends approval of the Major Site Plan subject to the following comments and conditions:

 

1. Provide the height to roofline on the all elevations as measured from the average finished grade. Please note the maximum building height is limited to 55 ft.

 

2. Ground floor to maintain 15 ft. height clearance for a minimum of 30 linear ft. to be shown on building permits prior to approval.

 

3. Payment of the in-lieu of fee for affordable housing, pursuant to Sec. 155.3709.K. must be received prior to Building Permit approval.

 

4. Revise the location of mechanical concrete pads that appear on the landscape buffer and sidewalk. Mechanical equipment is prohibited within required landscaping buffers and required sidewalks.

 

5.  Revise the ground floor plan to be consistent with the site plan (specifically review the ADA parking dimensions).

 

6. Standard conditions of approval and/or specifications required prior to Building Permit/Zoning Compliance Permit issuance:

             

                 a. Provide evidence that the development achieves at least 12 sustainable development 

                     points (TABLE 155.5802, Sustainable Development Options and Points).

 

                 b. Plans are subject to compliance with all applicable Code requirements, including 

                    but not limited to DRC comments issued for this site plan.

 

                 c. All overhead utilities located on the development site and/or along the public right-

                   of-way fronting the development site must be placed underground, pursuant to 

                     Section 155.5509.

 

                  d. Include a copy of the approved CPTED plan, approved by the Broward Sheriff’s       

                     Office.

 

                   e. Landscape and Irrigation Plans must comply with all Zoning Code requirements as   

                      verified by the City’s Urban Forestry Division.

.