File #: LN-138    Version: Name:
Type: DRC Submission Status: Held
File created: 5/28/2021 In control: Development Review Committee
On agenda: 8/4/2021 Final action: 8/4/2021
Title: POMPANO BEACH LIVE ROADWAYS SITE PLAN
Attachments: 1. 6.16.21 DRC Documents.zip, 2. 6.16.21. DRC Drawings.zip, 3. 8.4.21. DRC Documents.zip, 4. 8.4.21 DRC Drawings.zip, 5. 04.06.22 DRC Documents.zip, 6. 04-06-2022 DRC Drawings.zip

boardname

DEVELOPMENT REVIEW COMMITTEE

Meeting Date: APRIL 6, 2022

 

title

POMPANO BEACH LIVE ROADWAYS SITE PLAN

 

projectinfo

Request:                     Minor Site Plan

P&Z#                     21-12000022

Owner:                     Pompano Park JV NW Corner, LLC.

Project Location:                     Isle of Capri Circle

Folio Number:                     494203350040

Land Use Designation:                     RAC (Regional Activity Center)

Zoning District:                     PCD (Planned Commercial/Industrial)

Commission District:                     5 (Cyndy Floyd)

Agent:                      Michael Amodio (954-788-3400)

Project Planner:                     Max Wemyss (954-786-4671 /                                     max.wemyss@copbfl.com)

 

otherinfo

 

 

Summary:                     

The applicant is requesting MINOR SITE PLAN approval in order to reconstruct internal roadways identified as Lucky Lane and Palm Aire Drive, identified as phase 1 roadway improvements on the Live! District PCD Master Plan. The improved roadways contain 7-foot wide sidewalks and 5-foot wide bike lanes on both sides of the street, as well as lighting, street furniture, landscaping, and street trees.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Staff Conditions:                      

 

PLANNING

Plan Reviewer: Daniel Keester | daniel.keester@copbfl.com <mailto:daniel.keester@copbfl.com>

Status: Pending Development Order

-                     Land use for this parcel is currently RAC, amended September 24, 2019. The property was included in the platted subdivision "Arvida Pompano Park Plat," which was amended to restrict the property to 300,000 square feet of commercial use, 600,000 square feet of commercial recreation use, 450,000 square feet of office use, 500 mid-rise units and 350 room hotel. Based on the amended RAC, the Plat may need to be updated; however, it is not required for this proposal.

-                     The city has sufficient capacity to accommodate the proposal. 

 

 

ENGINEERING DEPARTMENT

Plan Reviewer: David McGirr | david.mcgirr@copbfl.com <mailto:david.mcgirr@copbfl.com>

Status: Pending Development Order

 

The following comments must be addressed prior to the submission of these plans to the Building Division for formal plan review and permitting:

PGD plans show water and sewer. Please change the title block to include water and sewer plans.

1.                     Submit/ upload the (BCEPMGD) Broward County Environmental Protection and Growth Management Division Surface Water Management permit or exemption for the proposed paving and drainage shown on the civil engineering drawings.

2.                     Submit / upload the (FDEP) Florida Department of Environmental Protection NPDES General Permit for the proposed storm water discharge from the proposed site construction activities.

3.                     Submit / upload the (FDEP) Florida Department of Environmental Protection (NOI) Notice of Intent for the proposed storm water discharge from the proposed site construction activities.

4.                     Submit / upload a copy the (BCEPGMD) Broward County Environmental Protection and Growth Management Division permit or written exemption from this agency for the proposed construction of the gravity sanitary sewer service lines shown on the civil engineering plans.

5.                     Submit / upload a copy the (FDEP) Florida Department of Environmental Protection permit or written exemption from this agency for the proposed construction of the gravity sanitary sewer service lines shown on the civil engineering plans.

6.                     Submit / upload a copy of the (FDEP) Florida Department of Environmental Protection permit or written exemption from this agency for the proposed potable water service line connections shown on the civil engineering drawing

7.                     Submit / upload a copy of the (FDOT) Florida Department of Transportation Utility construction permit for the proposed off-site potable water and sewer main or lines to be constructed within the road right-of-way of S. Powerline Rd.

8.                     Submit / upload a copy of the (FDOT) Florida Department of Transportation Driveway connection permit for the proposed driveway, roadway curb and gutter and sidewalk to be constructed within the road right-of-way of S. Powerline Rd.

9.                     Submit / upload a copy of the (FDOT) Florida Department of Transportation Driveway drainage connection permit for the proposed driveway, roadway curb and gutter and sidewalk to be constructed within the road right-of-way of S. Powerline Rd.

10.                     The proposed watermain and services, sanitary sewer connection to service this project and proposed drainage must be approved by the City of Pompano Beach Utilities Division.

11.                     Submit / Upload Broward County Traffic Engineering Division approval for the proposed off-site pavement marking and traffic signage plan.

15.                     Submit / Upload Broward County Highway Construction and Engineering Division for the proposed street roadway improvements (County roads). Submit copy of the approved permit or exemption. For the work to be constructed within the road right-of-way SW 3 St.

 

 

FIRE DEPARTMENT

Plan Reviewer: Jim Galloway | jim.galloway@copbfl.com

Status: Pending Development Order

This P&Z application is able to meet all of the Fire Department requirements at this time for Site Plan Review. However, the petitioner shall maintain all proper fire department access and water supply requirements as per chapter 18 of NFPA 1 as amended from time to time.

                     Additional comments may follow throughout the remainder of the permitting process. The buildings shall be in compliance with All NFPA Standards prior to receiving Fire Department approval.

 

BUILDING DIVISION

Plan Reviewer: Todd Stricker | todd.stricker@copbfl.com 

Status: No Comments

 

BSO

Plan Reviewer: Scott Longo | scott_longo@sheriff.org <mailto:scott_longo@sheriff.org>

Status: Review Complete No Comments

 

Disclaimer:

The services of an independent, experienced, qualified and certified Security Crime Prevention/ CPTED Consultant are highly recommended for objective and credible security review integrity.

This review does not guarantee a crime will never occur; it is an effort to mitigate opportunities for crime and to help avoid any present and future security deficiencies, conflicts, or liabilities that might occur without any review.

 

 

CRA

Plan Reviewer: Nguyen Tran | Nguyen.tran@copbfl.com <mailto:Nguyen.tran@copbfl.com>

Status: No Comments

 

 

 

UTILITIES

Plan Reviewer: Nathaniel Watson | nathaniel.watson@copbfl.com <mailto:nathaniel.watson@copbfl.com>

Status: As of 7-21-2021 - Resubmittal Required

 

1.                     Please note that additional comments may be forth coming contingent upon future submittals to the PAM and/or DRC review process.

2.                     Please procure an approved Broward County EPD Surface Water Management permit or exemption for the proposed site and off-site work. Required during official Bldg. E-plan submittal.

3.                     Please procure an approved Broward County Wastewater Collection permit for the proposed sanitary sewer system. Required during official Bldg. E-plan submittal.

4.                     Please procure an approved FDEP permit for the proposed water main infrastructure. Required during official Bldg. E-plan submittal.   

5.                     Please note that the City shall only accept ownership of utility assets newly installed as discussed and verified prior. Older existing utility assets within a dedicated right-of-way shall remain private until upgraded to City standard.        

6.                     Please note that utilities intended to be converted to City public assets via a dedicated public right-of-way shall be designed as point of service connections to adjacent private lots with water metered services, boxed City accessible sewer lateral cleanouts and/or manholes or stormwater system appurtenances shown just at or behind the recorded property line as determined by the City. Utility assets on private property shall be private after the point of service. Utility connections shall be shown out of driveway approaches for maintenance and access purposes.    

7.                     PGD plan 417 -CP102 proposes a 10” water main within a driveway approach adjacent to Palm Aire Drive. Please show the service within the adjacent green space and out of the driveway approach.

8.                     PGD plan 422 -CP102 proposes City owned water infrastructure within private property to be converted to public right-of-way. Please show the proposed water main extension main to the tapping valve proposing the existing water meter and back device removed upon system certification and acceptance by the City to also coincide with public right-of-way dedication of private roadway.              

9.                     Please note that meters 3” and larger are not stock items and are subject to an order lead time of 60 to 75 days after the items are paid. Please order accordingly.     

10.                     Please attach all pertinent 2019 City Engineering Standard Details as they apply.

 

 

LANDSCAPE REVIEW

Plan Reviewer: Wade Collum | wade.collum@copbfl.com <mailto:wade.collum@copbfl.com>

Status: Pending Development Order

                     Per meeting with the team

 

ZONING

Plan Reviewer: Max Wemyss | Max.Wemyss@copbfl.com <mailto:Max.Wemyss@copbfl.com>

Status: Pending Development Order

 

1.                     PD Regulations - Exhibit F - Palm Aire Drive and Lucky Lane are identified as Phase 1 Major Roads.

2.                     PD Regulations - Exhibit F1 - Palm Aire Drive and Lucky Lane are to be designed consistent with Street Section T9, T2, and T7.

 

 

SOLID WASTE AND RECYCLING

Plan Reviewer: Beth Dubow | beth.dubow@copbfl.com <mailto:beth.dubow@copbfl.com>

Status: Pending Development Order

 

NOTE:  Owners of commercial properties are responsible for securing garbage collection service directly from Waste Management, Inc. or current City franchise collector.

NOTE:  Recycling collection is not required, but it is suggested.  Recycling collection service may be obtained from a recovered materials hauler.

NOTE:  As stated in the Pompano Beach Code of Ordinances, Chapter 96, including Section 96.12(D)(1), all construction and demolition debris removal is the responsibility of the owner.  All solid waste generated within the geographic boundaries of Pompano Beach shall be collected by the franchise collector (Waste Management at the time of this writing) and disposed of as directed by the city disposal agreement.  All materials shall be generated from the property on which the materials are placed for removal.  Information regarding container size and hauling costs may be found in Chapter 96, Section 96.13.

NOTE:  Additional comments may be necessary based upon revisions, additional plans and/or documents.  Contact Beth Dubow at 954-545-7047 or beth.dubow@copbfl.com should you have any questions or concerns regarding this review.

 

PLEASE NOTE: Applications that require resubmission to the DRC have 45 days from the time of original DRC meeting in which to resubmit. Applications that fail to be resubmitted before the completion of these 45 days, or fail to receive a time extension from the Development Services Director, shall be considered withdrawn (§155.2304.B).