File #: LN-611    Version: Name:
Type: PZB Submission Status: Regular Agenda Ready
File created: 5/8/2024 In control: Planning and Zoning Board
On agenda: 7/24/2024 Final action:
Title: CHENEY BROTHERS POMPANO PROCESSING FACILITY
Attachments: 1. AAC Documents_06.04.2024.zip, 2. AAC Drawings_06.04.2024.zip, 3. PZB Documents 7-24-2024.zip, 4. PZB Drawings 7-24-2024.zip
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

boardname

PLANNING AND ZONING BOARD

Meeting Date: JULY 24, 2024

 

title

CHENEY BROTHERS POMPANO PROCESSING FACILITY

 

projectinfo

Request:                     Building Design

P&Z#                     22-12000051

Owner:                     GWB, LLC.

Project Location:                     2001 N. Andrews Avenue

Folio Number:                     484227260041, 484227260040, 484227260061

Land Use Designation:                     I (Industrial)

Zoning District:                     I-1 (General Industrial)

Commission District:                     4 (Beverly Perkins)

Agent:                      Matthew Wojciechowski (561-684-6141 / mwojciechowski@SNlandplan.com)

Project Planner:                     Lauren Gratzer (954-545-7792 / lauren.gratzer@copbfl.com)

 

otherinfo

Summary:                     

The applicant is requesting Major Site Plan approval in order to construct a new 71,873 square foot warehouse for a meat and fish processing center, along with associated parking and landscaping. The total footprint of all buildings is 58,657 square feet on a 146,965 square foot (3.37 acre) site, a total lot coverage of 40%. The site plan was reviewed by the Development Review Committee on April 3, 2024 and May 15, 2024.  Additionally, the project was approved by the Architectural Appearance Committee on June 4, 2024.

 

The property is located on the west side of N Andrews Avenue, between NW 22nd Street and NW 18th Street.

 

SITE PLAN REVIEW STANDARDS

An application for a Major Site Plan or Minor Site Plan shall be approved only on a finding that there is competent substantial evidence in the record that the development, as proposed:

 

1.                     Is consistent with the land use designation in the comprehensive plan;

 

The property has a land use designation of I (Industrial). The proposed industrial development is a compatible use for this land use category. The Development is consistent with the City of Pompano Beach Comprehensive Plan, and the Future Land Use Element Goals, Objectives and Policies contained therein:

 

Goal 01.00.00 The attainment of a living environment which provides the maximum physical, economic and social well-being for the City and its residents through the thoughtful and planned use and control of the natural and man-made environments that discourages urban sprawl, is energy efficient and reduces greenhouse gas emissions.

 

Policy 01.03.13

Future industrial land uses shall be located with access to major transportation facilities including highways, airports, railroads, and seaports.

 

Policy 01.06.12 Review all land use plan map amendments, rezonings and site plan applications to ensure that there is sufficient wastewater collection and treatment facilities, potable water resources available and if reuse water is available, require it be used, and that they pose no noxious impacts to the Biscayne Aquifer.

 

Policy 01.14.01 The City shall emphasize re-development and infill, which concentrates the growth and intensifies the land uses consistent with the availability of existing urban services and infrastructure in order to conserve natural and manmade resources.

 

Policy 01.14.07 All site plans will be reviewed for Crime Prevention Through Environmental Design (CPTED) design principles such as lighting, street design, natural surveillance, natural access control, and territorial reinforcement. CPTED infrastructure such as security lighting, security cameras, bollards and other access control methods will be required based on the specific needs of the project.

 

2.                     Complies with the applicable district, use, and intensity and dimensional standards of this Code (Articles 3, 4, and 5);

 

Article 3:  Zoning Districts

The proposed development complies with the standards for development within the I-1 (General Industrial) zoning district.

 

Article 4: Use Standards

The development proposes an industrial use that complies with the use-specific standards in Article 4: Use Standards and is consistent with section 155.4227.E. Food and/or Beverage Products Manufacturing (without slaughtering).

 

Article 5: Development Standards

See section 3 below.

 

3.                     Complies with the applicable development standards of this Code (Article 5);

 

The DRC and project applicant have worked together to present a project that satisfies the requirements of Article 5 for new development requiring Major Site Plan approval, with exception of the conditions listed for approval.

 

The project’s Building Design was approved by the Architectural Appearance Committee (AAC) on June 4, 2024.

 

As part of the Major Site Plan and Building Design application, the applicant has provided a narrative addressing how the project will achieve the required sustainability points. The project has met the required 12 sustainability points for non-residential development.

 

 

 

 

4.                     Complies with all other applicable standards in this Code;

 

The proposed site plan is in compliance with all other applicable standards of this Code.

 

5.                     Complies with all requirements or conditions of any prior applicable development orders or prior applicable approved plans on record.

 

There are no prior applicable development orders of record.

 

6.                     The concurrency review has been completed in accordance with Chapter 154 (Planning) of the Code of Ordinances;

 

Based on the calculations below, the proposed project complies with concurrency requirements.

 

Wastewater Treatment Demand                     5,836    gallons per day *

Water Treatment Demand                                          5,921    gallons per day *

Raw Water Demand                                                                7,475    gallons per day *

Park Acreage Required                                          N/A

School Impacts                     N/A

Transportation                     Transit fees paid to the Broward County to meet concurrency

Solid Waste Generation                     1,167 per meal (City has a contract with the Waste Management for disposal of all solid waste through 2032)

* The City has adequate capacity to serve the proposed project.

 

7.                     Is designed to provide safe, adequate, paved vehicular access between buildings within the development and streets as identified on the Broward County Trafficways Plan;

 

The project is designed to provide safe, adequate, and paved vehicular access from N Andrews Avenue, a street identified on the Broward County Trafficways Plan.

 

8.                     Complies with any applicable hazardous material licensing requirements in the Broward County Wellfield Protection Ordinance;

 

The property is not located within a wellfield protection area as identified on the Broward County Wellfield Protection Zones map.

 

 

9.                     Complies with crime prevention security strengthening and CPTED standards for natural surveillance, natural access control, territorial reinforcement, maintenance and activity support;

 

As part of the Major Site plan and Building Design application, the applicant has developed a separate CPTED security plan, which addresses the CPTED standards for natural surveillance, natural access control, territorial reinforcement, maintenance and activity support.

 

10.                     Complies with adopted Fire Codes and Standards per City Code Section 95.02.

 

The proposed site plan was reviewed by a Fire Plans Examiner during DRC and will be required to meet all applicable standards before building permits are approved.

 

11.                     Considers and mitigates any potential adverse impacts on environmentally sensitive lands identified by the City Comprehensive Plan or Broward County Land Use Plan.

 

The proposed development is not within an area that will have impact on environmentally sensitive lands as defined in the Broward County Land Use Plan.

 

12.                     Complies with the approved Transportation Corridor Study, unless in direct conflict with another Zoning code provision.

 

The proposed development is not located within an area identified on the Transportation Corridor Study.

 

DEPARTMENT RECOMMENDATION

 

Pursuant to §155.2304.C, Applications Subject to Staff Recommendation, the Development Services Director has compiled the department reports from the Development Review Committee (DRC) meeting which are recorded on file with the Department of Development Services.  Should the Board find that the application has provided competent, substantial evidence to satisfy the review standards for Major Site Plan approval, the Development Services Department recommends approval of the Major Site Plan subject to the following comments and conditions: 

 

1.                     The following items shall be provided prior to building permit approval:

a.                     Documentation of approval for the proposed 15-foot abandonment of the northern utility easement.

b.                     A Unity of Title for the three subject folios.

c.                     The standard easement agreement form shall be submitted for the proposed construction within the utility easements along the perimeter of the property.

 

2.                     Standard Conditions of Approval and/or Specifications required prior to Building Permit / Zoning Compliance Permit issuance:

a.                     The applicant shall provide evidence of compliance for the points used for the Sustainability Narrative as submitted to the PZB by time of building permit approval in accordance with Table 155.5802: Sustainable Development Options and Points.

b.                     Plans are subject to compliance with all applicable Code requirements, including but not limited to DRC comments issued for this site plan.

c.                     Landscape and Irrigation Plans must comply with all Zoning Code requirements as verified by the City’s Urban Forestry Division.

d.                     A copy of the CPTED plan approved by the Broward Sheriff’s Office must be submitted for Zoning Compliance Permit approval.