File #: 25-590    Version: 1 Name:
Type: Resolution / Regular Agenda Status: Regular Agenda Ready
File created: 9/17/2025 In control: City Commission
On agenda: 10/28/2025 Final action:
Title: A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO APPLY FOR THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION REVOLVING LOAN PROGRAM FOR DRINKING WATER FACILITIES; UPON APPROVAL, EXECUTE THE CORRESPONDING LOAN AGREEMENT, CARRYING OUT ALL LOAN RESPONSIBILITIES UNDER THE AGREEMENT; ESTABLISHING PLEDGED REVENUES; PROVIDING FOR CONFLICTS; PROVIDING FOR SEVERABILITY; PROVIDING AN EFFECTIVE DATE. (Fiscal Impact: $30,000,000 with $6,000,000 principal loan forgiveness)
Attachments: 1. City Manager Memo.pdf, 2. 2025-265 - Resolution.pdf, 3. City Attorney Memo.pdf, 4. DWSRF Program Loan Application_3.9.22.pdf, 5. 2025 Planning Document - Water Facility Plan Summary & Recommendations & Revisions.pdf, 6. Pompano Beach Revised Facility Plan Plan Specs Approval Letter- July 16 2025.pdf, 7. Resolution 2023-200 Approval of Loan DW06249A.pdf, 8. Resolution 2024-184 Approval of Water Facility Plan.pdf, 9. Ordinance No. 2024-10 Adoption Water Wastewater Rate.pdf, 10. Ordinance No. 2025-01 Adopttion Water Wastewater Series 2024 Bonds.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO APPLY FOR THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION REVOLVING LOAN PROGRAM FOR DRINKING WATER FACILITIES; UPON APPROVAL, EXECUTE THE CORRESPONDING LOAN AGREEMENT, CARRYING OUT ALL LOAN RESPONSIBILITIES UNDER THE AGREEMENT; ESTABLISHING PLEDGED REVENUES; PROVIDING FOR CONFLICTS; PROVIDING FOR SEVERABILITY; PROVIDING AN EFFECTIVE DATE.

(Fiscal Impact: $30,000,000 with $6,000,000 principal loan forgiveness)

 

staffcontact

(Staff Contact: Renuka Mohammed)

 

summary

Summary Explanation/Background:

The City of Pompano Beach is seeking Commission approval to apply for and accept funding through the Florida Department of Environmental Protection (FDEP) Drinking Water State Revolving Fund (DWSRF) under loan application DW0624C0. The requested $30 million loan will fund Phase I of the Emerging Contaminants Water Treatment Plant Upgrades, specifically the buildout of the City’s nanofiltration (NF) facility to address Federal and State regulations on per- and polyfluoroalkyl substances (PFAS), which go into effect in 2029.

Under the proposed financing terms, $6 million (20%) of the loan will be forgiven, with the remaining $24 million to be repaid over 20 years at a below-market interest rate. The loan will be supplemented by existing bond proceeds authorized under Ordinance 2025-01 and PFAS Litigation claims.

This project is essential to achieving compliance with new Federal and State PFAS standards set by the U.S. EPA and ensuring long-term protection of public health and drinking water quality for the City’s utility customers.

This funding opportunity is contingent upon the submission of the complete application by the deadline of December 11, 2025. Failure to meet this deadline will result in removal from consideration for inclusion in this priority listing cycle.

Prior Actions
                     Resolution 2023-200: $9.595M DWSRF loan (100% loan forgiveness)
                     Resolution 2024-184: Water Facility Plan approval
                     Ordinance 2024-10: Water & Sewer rate adoption
                     Ordinance 2025-01: Bond issuance authorization

Recommendation
                     Approve and authorize the Utilities Department to submit and finalize DWSRF Loan Application DW0624C0 in the amount of $30,000,000, with $6,000,000 in loan  forgiveness.

 

Origin of request for this action: Utilities

Fiscal impact and source of funding: $24,000,0000 financed over the maximum SRF 20-year term and $6,000,000 with principal loan forgiveness

 

pagebreak1

 

 

 

 

 

 

 

strategicplan_emblem_field

RStrategic Plan Initiative

 

pagebr

 

 

 

 

 

 

strategicplan_description_field

Goal 4 (item 6) -Superior Capacity for Growth through Quality, Sustainable Development - Expand and enhance utility infrastructure - water, wastewater and stormwater