Skip to main content

 

File #: 26-02    Version: 1 Name:
Type: Resolution / Regular Agenda Status: Regular Agenda Ready
File created: 9/30/2025 In control: City Commission
On agenda: 10/14/2025 Final action:
Title: A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE A LICENSE AGREEMENT AND SYNCHRONIZATION AGREEMENT BETWEEN THE CITY OF POMPANO BEACH AND THE FLORIDA EAST COAST RAILWAY, LLC (FEC) TO INSTALL IMPROVEMENTS AND TO SYNCHRONIZE RAILROAD GRADE CROSSING AND TRAFFIC CONTROL DEVICES WITHIN ATLANTIC BOULEVARD AND DIXIE HIGHWAY INTERSECTION AND FEC RIGHT-OF-WAY AND TO PROVIDE ANNUAL MAINTENANCE OF THE RAILROAD CROSSING WITHIN THE SUBJECT INTERSECTION; PROVIDING AN EFFECTIVE DATE. (Fiscal Impact: $3,045,847.86)
Attachments: 1. Memo to City Commission-FEC Agreements.pdf, 2. Memo to CA for FEC Agreements - Dixie Highway .pdf, 3. City Attorney's Comm. 2025-923.pdf, 4. Resolution 2025-222.pdf, 5. 20250717 - 333.14 (+754) - SR 814 (Atlantic Boulevard) - 272533K - License Agreement - FEC-CITY - AGMT PACKAGE (r2).pdf, 6. 20250717 (v2) - 333.14 (+754) - SR 814 (Atlantic Boulevard) - 272533K - Synch Agreement PKG.pdf, 7. Location Map -FEC.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE A LICENSE AGREEMENT  AND SYNCHRONIZATION AGREEMENT BETWEEN THE CITY OF POMPANO BEACH AND THE FLORIDA EAST COAST RAILWAY, LLC (FEC) TO INSTALL IMPROVEMENTS AND TO SYNCHRONIZE RAILROAD GRADE CROSSING AND TRAFFIC CONTROL DEVICES WITHIN ATLANTIC BOULEVARD AND DIXIE HIGHWAY INTERSECTION AND FEC RIGHT-OF-WAY AND TO PROVIDE ANNUAL MAINTENANCE OF THE RAILROAD CROSSING WITHIN THE SUBJECT INTERSECTION; PROVIDING AN EFFECTIVE DATE.

(Fiscal Impact: $3,045,847.86)

 

staffcontact

(Staff Contact: Fernand Thony)

 

summary

Summary Explanation/Background:

Staff is seeking City Commission approval of a Resolution to execute 2 agreements with Florida East Coast Railway (FEC) for the crossing site on Atlantic Boulevard: a license agreement to install railway infrastructure improvements and a synchronization agreement for traffic control devices and interconnection with the Dixie Highway intersection’s signalization system. The equipment, required for the aforementioned improvements is made of long lead items which also requires specialty personnel for the installation. These improvements will be performed by FEC’s own authorized contractor for an estimated cost of $2,645,847.86 and are scheduled to take place during next summer school recess (2026). Staff is recommending an additional $400,000.00 in contingency to account for potential variance in FEC’s order of magnitude estimate during execution of the work for a grand total funding of $3,045,847.86. Because $1,500,000.00 was already budgeted for these specific improvements, the resulting $1,545,847.86 difference in cost will be paid to FEC with escalation funding already awarded to the project by Broward County Surtax.

 

Origin of request for this action: GO Bond Department

Fiscal impact and source of funding: $3,045,847.86:  $1,500,000 Account #326-7672-539-6512; $1,545,847.86 Account # 113-7633-530-6512 (reimbursed by surtax funds from County)

 