title
A RESOLUTION OF THE POMPANO BEACH COMMUNITY REDEVELOPMENT AGENCY (CRA), APPROVING AND AUTHORIZING THE PROPER OFFICIALS TO EXECUTE A CHANGE ORDER IN THE AMOUNT OF $88,066.01 PURSUANT TO THE CONSTRUCTION-MANAGER-AT-RISK CONTRACT BETWEEN THE CRA AND MBR CONSTRUCTION, INC., FOR IMPROVEMENTS RELATING TO THE BACKYARD PROJECT; PROVIDING AN EFFECTIVE DATE.
(Fiscal Impact: $88,066.01)
staffcontact
(Staff Contact: Horacio Danovich/Nguyen Tran)
summary
Summary Explanation/Background:
On September 15, 2020, via Resolution 2020-43, the CRA executed a CMAR contract with MBR Construction, Inc. for Old Town’s Backyard improvements in the amount of $1,620,000.00.
MBR has submitted a second Change Order in the amount of $88,066.01 for additional site modifications and associated cost for the The Backyard project.
Origin of request for this action: Staff
Fiscal impact and source of funding: 150-7590-539.65-12 (17312) - Downtown Pompano Above Ground Improvements
pagebreak1
strategicplan_emblem_field
pagebr
strategicplan_description_field