Title: A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, AUTHORIZING THE APPROPRIATION OF $600,000 FROM THE UTILITIES FUND BALANCE TO FUND THE SE 9TH AVENUE FORCE MAIN PIPE BURSTING IN-KIND PROJECT; PROVIDING FOR PURPOSE; PROVIDING FOR IMPLEMENTATION; PROVIDING FOR AN EFFECTIVE DATE. (Fiscal Impact: $600,000)
Attachments: 1. City Manager Memo.pdf, 2. City Attorney Memo.pdf, 3. 2026-58 Resolution.pdf, 4. UT Consent Order Memo SFCO 25-0457.pdf, 5. Consent Order-OGC #25-0457 COPB FDEP Full Execution.pdf, 6. City of Pompano Beach SFCO 25-0457 In Kind Project Proposal.pdf signed 112525.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, AUTHORIZING THE APPROPRIATION OF $600,000 FROM THE UTILITIES FUND BALANCE TO FUND THE SE 9TH AVENUE FORCE MAIN PIPE BURSTING IN-KIND PROJECT; PROVIDING FOR PURPOSE; PROVIDING FOR IMPLEMENTATION; PROVIDING FOR AN EFFECTIVE DATE.

(Fiscal Impact: $600,000)

 

staffcontact

(Staff Contact: Renuka Mohammed/ Joshua Watters)

 

summary

Summary Explanation/Background:

The Utilities Department seeks City Commission approval to appropriate $600,000 from the Utilities Fund Balance to fund an in-kind project submitted to the Florida Department of Environmental Protection (FDEP) to offset penalties under Consent Order No. 25-0457. The Consent Order pertains to six agreed-upon sanitary sewer overflow (SSO) violations that occurred between 2022 and 2023. In lieu of penalties, the Department opted to fund the SE 9 Avenue Force Main Pipe Bursting Project, a location that is in need of wastewater improvements but is unfunded. The project will further strengthen the overall wastewater infrastructure, reduce the likelihood of future SSOs, and meet the requirement for non-preallocated funding. Staff recommends approval of the budget amendment, which increases the Utility R&R Fund appropriation authority by $600,000.

 

Origin of request for this action: Utilities

Fiscal impact and source of funding: $600,000 to be allocated to account 420-7779-535-65-12

 

pagebreak1

 

 

 

 

 

 

 

strategicplan_emblem_field

RStrategic Plan Initiative

 

pagebr

 

 

 

 

 

 

strategicplan_description_field

Strategic Plan: Goal 4 (Item 6): Superior Capacity for Growth through Quality, Sustainable Development - Expand and enhance utility infrastructure - water, wastewater and stormwater.

Comprehensive Plan Goal 6: Sanitary Sewer service shall be provided and maintained in an efficient and cost-effective manner that will ensure public health, safety, and quality of life, while protecting the environment