title
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, AMENDING THE CAPITAL IMPROVEMENT PLAN FOR THE CITY OF POMPANO BEACH FOR FISCAL YEARS 2020 THROUGH 2024 TO INCLUDE A PROJECT FOR THE DESIGN AND CONSTRUCTION OF A NEW BSO SUBSTATION; ESTABLISHING THE APPROPRIATE BUDGET FOR FY 2020; PROVIDING AN EFFECTIVE DATE.
(Fiscal Impact: $874,500)
staffcontact
(Staff Contact: Vince Wooten/Tammy Good/Suzette Sibble)
summary
Summary Explanation/Background:
This project consists of designing and constructing a new 2500 sf single story substation and site development for the Broward Sheriff’s Office located at 441 NW 27 Avenue. This new substation will entrench police presence in the area to negate/reduce criminal activity, thus stabilizing the neighborhood and making it a safer and better place to live.
Origin of request for this action: City Manager’s Office/BSO
Fiscal impact and source of funding: $874,500 from account 302-7676-521-65-03 & 302-7676-521-65-12 with the attached budget adjustment
pagebreak1
strategicplan_emblem_field
pagebr
strategicplan_description_field