File #: 25-409    Version: 1 Name:
Type: Approval Request / Regular Agenda Status: Passed
File created: 6/5/2025 In control: City Commission
On agenda: 9/9/2025 Final action: 9/9/2025
Title: Approving and authorizing the award of ITB #25-030 for runway 10-28 rehabilitation and correction of expansive pavement on runway 10 end to the lowest responsive, responsible bidder, General Asphalt Co. in the amount of $5,259.091.50, and authorizing the proper city officials to execute the contract as provided in ITB25-030. (Fiscal Impact: $5,259,091.50 - 95% from FAA grant; 2.5% from FDOT grant; 2.5 % City Match)
Attachments: 1. ITB25-030 - PMP RWY 10-28 Rehab - Volume I Front End Specifications (1).pdf, 2. ITB25-030 - PMP RWY 10-28 Rehab - Volume II Technical Specifications Addendum - 2.pdf, 3. ITB25-030 - PMP RWY 10-28 Rehab - Volume III Drawings Addendum - 2.pdf, 4. Exhibit C Insurance Requirements.pdf, 5. Memorandum - 25-017 - Resolution to award ITB25-030 to General Asphalt Co. Inc.pdf, 6. ITB25-030 Runway 10-28 Rehabilitation and Correction of Expansive Pavement HDR Recommendation Letter.pdf, 7. PMP-SOG-3-12-0066-011-2025-Grant Agreement (part 1) - signed.pdf

title

Approving and authorizing the award of ITB #25-030 for runway 10-28 rehabilitation and correction of expansive pavement on runway 10 end to the lowest responsive, responsible bidder, General Asphalt Co. in the amount of $5,259.091.50, and authorizing the proper city officials to execute the contract as provided in ITB25-030.

(Fiscal Impact: $5,259,091.50 - 95% from FAA grant; 2.5% from FDOT grant; 2.5 % City Match)

 

staffcontact

(Staff Contact: Dr. Tammy Good)

 

summary

Summary Explanation/Background:

Invitation to Bid (ITB) ITB25-030 was issued to obtain bids to perform major rehabilitation of runway10-28. The 2021 FDOT pavement management program (PMP) report listed the runway’s pavement condition index (PCI) at 64, in ‘Fair’ condition. FAA policy is to perform major rehabilitation of asphalt general aviation runways once they are below a PCI of 65.  Bid award is recommended to the lowest responsive, responsible bidder, General Asphalt Co., Inc., at a cost of $5,259,091.50.  The City has applied for a grant, which would fund 97.5% of this project. City Commission approval of this contract award is requested. The sample Construction Agreement advertised in the solicitation will be completed with the details of lowest responsive responsible bidder with no material deviations.

 

Origin of request for this action: Staff

Fiscal impact and source of funding: Fiscal Impact: $5,259,091,50; 95% from FAA grant; 2.5% from FDOT grant; 2.5% City Match.

 