File #: 26-37    Version: Name:
Type: Resolution / Regular Agenda Status: Failed
File created: 10/15/2025 In control: City Commission
On agenda: 12/9/2025 Final action:
Title: A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE AWARD OF RFP25-001 OCEANSIDE PARKING GARAGE DESIGN-BUILD PROJECT TO THE HIGHEST RANKED PROPOSER, THE WHITING-TURNER CONTRACTING CO., IN THE AMOUNT OF $32,876,690, AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE THE CONTRACT BETWEEN THE CITY OF POMPANO BEACH AND THE WHITING-TURNER CONTRACTING CO.; PROVIDING AN EFFECTIVE DATE. (Fiscal Impact: Design & Pre-Construction $3,037,041.00 available; Construction $29,839,649.00 (financed); Total $32,876,690.00) POSTPONED FROM NOVEMBER 13, 2025
Attachments: 1. City Attorney's Communication Memorandum #2026-33.pdf, 2. Resolution 2026-24.pdf, 3. Commission Memorandum 26-01.pdf, 4. Agenda Memo.pdf, 5. Attachment 1 - Garage Design Concept - WT.pdf, 6. Attachment 2 - Garage sizing.pdf, 7. Attachment 3 - Preliminary Debt Service Schedule.pdf, 8. Attachment 3.1 - Preliminary debt service schedule old town garage.pdf, 9. Attachment 4- Pkg Fund Pro Forma - WT Agenda Item.pdf, 10. Attachment 5 - Parking Rates Survey.xlsx, 11. Design-Build AIA-Contract #12818.pdf, 12. Proposed Parking Garage Design.pdf, 13. Conceptual Site Plan_Location Map.pdf, 14. Oceanside Parking Garage Schedule of Values (Cost).pdf, 15. Whiting-Turner Solicitation Proposal.pdf, 16. Selection Committee Ranking_Scoring Sheets.pdf, 17. Bid Recommendation Tabulation.pdf, 18. Exhibit A - Request for Proposals (RFP25-001).pdf, 19. Exhibit B - General Conditions.pdf
title
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE AWARD OF RFP25-001 OCEANSIDE PARKING GARAGE DESIGN-BUILD PROJECT TO THE HIGHEST RANKED PROPOSER, THE WHITING-TURNER CONTRACTING CO., IN THE AMOUNT OF $32,876,690, AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE THE CONTRACT BETWEEN THE CITY OF POMPANO BEACH AND THE WHITING-TURNER CONTRACTING CO.; PROVIDING AN EFFECTIVE DATE.
(Fiscal Impact: Design & Pre-Construction $3,037,041.00 available; Construction $29,839,649.00 (financed); Total $32,876,690.00)

POSTPONED FROM NOVEMBER 13, 2025

staffcontact
(Staff Contact: Tammy Good)

summary
Summary Explanation/Background:
Request for Proposal (RFP) No. RFP25-001 was issued to solicit proposals in response to the attached Request for Proposals for Design-Build Services for the Construction of a Parking Garage located at 109 N. Ocean Boulevard (A1A), Pompano Beach, FL 33060, also referred to as the Oceanside Parking Garage (109 N. Ocean Blvd.). The City will initially commit only to the Design and Pre-Construction portion of the proposal, in the amount of $3,037,041.00, until the design phase is completed. Upon the City's approval of the final design (expected early fall FY 2027), the remaining portion of the contract covering construction costs will be contingent upon the City's ability to issue debt upon the completion of the design process. All financing documents will be brought back to the City Commission for approval. WT contract for construction is contingent upon approval and issuance of the debt. See attached memo for additional discussion.

Origin of request for this action: Staff
Fiscal impact and source of funding: Design & Pre-Construction $3,037,041.00 account#473-7719-545-65- 03; Construction $29,839,649.00 from debt proceeds; Total $32,876,690.00