File #: LN-118    Version: 1 Name:
Type: DRC Submission Status: Passed
File created: 4/22/2021 In control: Development Review Committee
On agenda: 5/5/2021 Final action: 5/5/2021
Title: FIRE STATION 52 & FUEL DEPOT SITE PLAN
Attachments: 1. 5.5.2021_DRC Documents
boardname
DEVELOPMENT REVIEW COMMITTEE
Meeting Date: MAY 5, 2021

title
FIRE STATION 52 & FUEL DEPOT SITE PLAN

projectinfo
Request: Minor Site Plan
P&Z# 21-12000013
Owner: City of Pompano Beach
Project Location: 10 SW 27 Ave.
Folio Number: 494204410010
Land Use Designation: C (Commercial)
Zoning District: B-2 (Community Business)
Commission District:|910|Agent: Jose Aguila (561-276-4951)
Project Planner: Pamela Stanton (954-786-5561 / pamela.stanton@copbfl.com)

otherinfo


Summary:
Fire Station 52 was approved under PZ320-12000014 as a Major Site Plan. The City acquired the property to the north of Fire Station 51 and recorded a Unity of Title to unify the two properties. The design of the building, vehicular use areas and circulation remain unchanged, and will be shifted to the north, immediately south of the access road that runs parallel to West Atlantic Blvd. In addition to the shift in these elements, the City is proposing a one pump fueling dispenser, fueling canopy, and 15,000 gallon diesel fuel tank to use for City vehicles. The new "Fuel Depot" will be located south of the new Fire Station at the south end of the site.
Staff Conditions:
PLANNING
Plan Reviewer: Daniel Keester, daniel.keester@copbfl.com
Status: Review Complete Pending Development Order
-Land use for this parcel is Community Facilities, the zoning is B-2. A Fire Station (P&Z: 20-12000014), with the addition of a fuel depot (this minor site plan application), is a permitted use in this zoning district. The proposal is in conformance with the plat note, which limits the property to 20,000 square foot fire station.
-The City has sufficient capacity to accommodate the proposal.

ENGINEERING DEPARTMENT
Plan Reviewer: David McGirr, david.mcgirr@copbfl.com
Status: Review Complete Pending Development Order
The following comments must be addressed prior to the submission of these plans to the Building Division for formal plan review and permitting:

Will these Utility changes be added ...

Click here for full text