File #: 21-528    Version: Name:
Type: Ordinance / Regular Agenda Status: Second Reading
File created: 5/11/2021 In control: City Commission
On agenda: 6/8/2021 Final action:
Title: P.H. 2021-74: (PUBLIC HEARING 1ST READING) AN ORDINANCE OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE AN AGREEMENT BETWEEN THE CITY OF POMPANO BEACH AND GIANNETTI CONTRACTING CORPORATION FOR THE LYONS PARK STORMWATER AND WASTEWATER IMPROVEMENTS PROJECT; PROVIDING FOR SEVERABILITY; PROVIDING AN EFFECTIVE DATE. (Fiscal Impact: $17,659,117.70) SECOND READING: MAY 25, 2021
Attachments: 1. 21-36 Req for Reso Lyons Park Construction Contract.pdf, 2. 2021-185 Ordinance.pdf, 3. 2021-620 City Attorney's Communication.pdf, 4. E-12-21 Giannetti Contracting Corp Lyons Park_Signed.pdf, 5. COI_Giannetti Contracting Corp 5.10.21.pdf, 6. Exhibit A_01_RFP-E-12-21_Lyons_Park_Stormwater_and_Wastewater_Improvements-Revision.pdf, 7. 21-38 Ordinance Memorandum City Commission Lyons Park.pdf, 8. Pending_Payment & Performance Bonds_Giannetti.docx, 9. Lyons Park Plans_Bid Set.pdf

title

P.H. 2021-74: (PUBLIC HEARING 1ST READING)

AN ORDINANCE OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE AN AGREEMENT BETWEEN THE CITY OF POMPANO BEACH AND GIANNETTI CONTRACTING CORPORATION FOR THE LYONS PARK STORMWATER AND WASTEWATER IMPROVEMENTS PROJECT; PROVIDING FOR SEVERABILITY; PROVIDING AN EFFECTIVE DATE.

(Fiscal Impact: $17,659,117.70)

 

SECOND READING: MAY 25, 2021

 

staffcontact

(Staff Contact: Matthew Kudrna)

 

summary

Summary Explanation/Background:

The Request for Proposals E-12-21 was issued to select a firm to provide construction services to the City for The Lyons Park Stormwater and Wastewater Improvement Project, the opening was on March 15, 2021.

The Lyons Park area suffers from flooding problems as documented in the City Stormwater Master Plan. This project will improve the drainage systems within the Lyons park neighborhood. The sanitary sewer lines within the Lyons Park Neighborhood are in the rear yard easements of the properties and this project will relocate the sewers to the street within the City right-of-way.

At the April 27, 2021 Commission meeting Consent Agenda Item #21-479 passed, approving the ranking order for RFP E-12-21, Lyons Park Stormwater and Wastewater Improvements, and authorize staff to negotiate a contract with the highest ranked firm, Giannetti Contracting Corp.

 

Origin of request for this action: Engineering

Fiscal impact and source of funding: $17,659,117.70 broken down as follows.  $9,456,715.95 from the Water and Wastewater Revenue Bonds and $8,202,401.75 from the Stormwater Utility Revenue Bonds.

 