Title: A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE WORK AUTHORIZATION NO. 5 IN THE AMOUNT OF $195,820.00 PURSUANT TO THE CONTRACT FOR CONSULTING/PROFESSIONAL SERVICES BETWEEN THE CITY OF POMPANO BEACH AND TETRA TECH, INC. FOR HURRICANE HARDENING AND CONSTRUCTION ADMINISTRATION SERVICES FOR THE WATER TREATMENT PLANT FILTER/ADMINISTRATION BUILDING WITH EXTERIOR TANKS AND MEMBRANE BUILDING; PROVIDING AN EFFECTIVE DATE. (Fiscal Impact: $195,820.00)
Sponsors: Tammy Good
Attachments: 1. Memorandum 18-73 to City Attorney, 2. Memorandum 2018-1183 from City Attorney, 3. Resolution 2018-308, 4. Memorandum 18-97 to Commission, 5. Work Authorization 5, 6. Design Scope and Fees, 7. Hourly Design Fees, 8. WTP Site Map, 9. Hurricane Hardening Study, 10. Certificate of Insurance, 11. Approved Ordinance No. 2016-26

title

A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE WORK AUTHORIZATION NO. 5 IN THE AMOUNT OF $195,820.00 PURSUANT TO THE CONTRACT FOR CONSULTING/PROFESSIONAL SERVICES BETWEEN THE CITY OF POMPANO BEACH AND TETRA TECH, INC. FOR HURRICANE HARDENING AND CONSTRUCTION ADMINISTRATION SERVICES FOR THE WATER TREATMENT PLANT FILTER/ADMINISTRATION BUILDING WITH EXTERIOR TANKS AND MEMBRANE BUILDING; PROVIDING AN EFFECTIVE DATE.

(Fiscal Impact: $195,820.00)

 

staffcontact

(Staff Contact: A. Randolph Brown/Tammy Good)

 

summary

Summary Explanation/Background:

Engineering design and construction administration services for the identified hurricane hardening elements at the Water Treatment Plant for the Filter/Administration Building, Exterior Tanks and the Membrane Building. Based on Tetra Tech’s Hurricane Hardening Study dated June 30, 2016, the firm will provide design documents and other engineering services as described in Part II of the proposal for the building improvements identified in the study in addition to addressing life safety items.

 

Origin of request for this action: Utility Department

Fiscal impact and source of funding: 420-7567-533.65-03

 

pagebreak1

 

 

 

 

 

 

 

strategicplan_emblem_field

                                                   

 

pagebr

 

 

 

 

 

 

strategicplan_description_field

                                                   

 

file

TETRA TECH, INC. - WORK AUTH. 5