File #: 19-263    Version: Name:
Type: Ordinance / Regular Agenda Status: Passed
File created: 2/22/2019 In control: City Commission
On agenda: 3/26/2019 Final action: 3/26/2019
Title: P.H. 2019-39: (PUBLIC HEARING 2ND READING) AN ORDINANCE OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE AN AGREEMENT FOR PROFESSIONAL CONSULTING SERVICES BETWEEN THE CITY OF POMPANO BEACH AND T.Y. LIN INTERNATIONAL, FOR THE SE 5TH AVENUE BRIDGE IMPROVEMENTS; PROVIDING FOR SEVERABILITY; PROVIDING AN EFFECTIVE DATE. (Fiscal Impact: $439,278.48) FIRST READING: MARCH 12, 2019
Attachments: 1. Memo to Commission, 2. City Attorney Communication #2019-548, 3. Ordinance SE 5 Avenue Bridge, 4. Memo to City Attorney SE 5 Ave Bridge Signed, 5. SE 5 Avenue Bridge Location Map, 6. SE 5th Ave Bridge Proposed Rendering, 7. SE 5th Ave Bridge Elevations, 8. Ty Lin International V5 SE 5th St, 9. Exhibit A Scope of Work, 10. Exhibit B Insurance Requirements, 11. Exhibit C RFP E.31.18 and Cons. Resp.

title

P.H. 2019-39: (PUBLIC HEARING 2ND READING)

AN ORDINANCE OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE AN AGREEMENT FOR PROFESSIONAL CONSULTING SERVICES BETWEEN THE CITY OF POMPANO BEACH AND T.Y. LIN INTERNATIONAL, FOR THE SE 5TH AVENUE BRIDGE IMPROVEMENTS; PROVIDING FOR SEVERABILITY; PROVIDING AN EFFECTIVE DATE.

(Fiscal Impact: $439,278.48)

 

FIRST READING: MARCH 12, 2019

 

staffcontact

(Staff Contact: Horacio Danovich)

 

summary

Summary Explanation/Background:

Staff is seeking approval of a contract between the City of Pompano Beach (“City”) and T. Y. Lin International (“TY”) in the sum of $439,278.48 to provide professional services for the G. O. Bond funded project “SE 5th Avenue Bridge Improvements” (see Location Map). This project was duly advertised as E-16-18 Design and Consulting Services for Five Bridges within City Limits and TY was ranked no. 1. The City Commission approved the rankings on 1/8/2019. Attached is a copy of the contract documents including the proposed Scope of Work (Exhibit “A”) submitted by the firm and reviewed by staff for accuracy and completeness.

 

Origin of request for this action: G.O. Bond

Fiscal impact and source of funding: $439,278.48, account 318-7638-530.65-03 OUTSIDE CONSULTING/DESIGN

 