File #: LN-05    Version: Name:
Type: PZB Submission Status: Passed
File created: 9/14/2020 In control: Planning and Zoning Board
On agenda: 11/18/2020 Final action: 11/18/2020
Title: UNIVERSAL HEAT & AIR
Attachments: 1. 10/6 AAC Meeting Drawings, 2. 11.18.2020_PZB Drawings.zip, 3. 11.18.2020_PZB Documents.zip, 4. 10/6 AAC Meeting Documents
boardname
PLANNING AND ZONING BOARD/LOCAL PLANNING AGENCY
Meeting Date: NOVEMBER 18, 2020

title
UNIVERSAL HEAT & AIR

projectinfo
Request: Major Site Plan
P&Z# 18-12000037
Owner: Michael Forgione
Project Location: 980 SW 12th Avenue
Folio Number: 494202000570
Land Use Designation: I
Zoning District: I-1
Commission District:|910|Agent: Michael Forgione (954-605-9018)
Project Planner: Jae Eun Kim

otherinfo


Summary:

The following is a summary of information on the subject property. The applicant is requesting Major Site Plan approval in order to construct a building for a contractor's office and warehouse with associated parking and landscaping areas. The building has a 7,184 sq. ft. building footprint including a mezzanine. The total footprint of the proposed building is 6,002 sq. ft. on a 24,505 sq. ft. (0.57 acre) site. The total lot coverage is 24.5%. This proposed development was reviewed by the Development Review Committee on February 20, 2019 and was reviewed by the Architectural Appearance Committee on October 6, 2020.
The property is currently vacant and located west of S. Andrews Avenue (SW 12 Av) and south of SW 8 Street.

The project necessitated two applications in advance of placement for this Board meeting. The following is a brief summary of approvals obtained:

* Variance 19-11000011: Obtained approval of an interior side yard setback of 0 feet along the south property line and a two-way drive aisle at a width of 20 feet on May 16, 2019.
* INSTR # 116714543: Easement and Agreement for ingress and egress to the neighboring property, south of the subject property in order to provide Fire access.

Staff Conditions:
SITE PLAN REVIEW STANDARDS
An application for a Major Site Plan or Minor Site Plan shall be approved only on a finding that there is competent substantial evidence in the record that the development, as proposed:
1. Is consistent with the comprehensive plan;

The Design Team believes the proposed project is consistent...

Click here for full text